021 Paving Schedule - STARTING AUG. 2ND

Important Notice:

Starting the week of August 2nd, The H&K Group will begin repaving the following streets:

TENTATIVE order of repaving - SUBJECT TO CHANGE DUE TO WEATHER OR EQUIPMENT BREAKDOWN:

1. Meadow Lane (Colebrook Road - Forney Road)

2. W. Oak Street (S. Mill Street - Meadow Lane)

3. Church Road (W. Oak Street - TWP Line)

4. Royal Road (W. Oak Street - TWP Line)

5. Bricker Lane (S. Mill Street to Meyerlo Lane and Anne Lane - TWP line)

6. S. Mill Street (Bricker Lane - TWP line)

7. Dairy Road (Walnut Street - 2nd turn)

8. Walnut Street (16th Street - 22nd Street)

Some roads will be temporarily closed during paving but will remain open to local traffic only. Please pay special attention to flaggers and construction crews while they are in the area. Please detour around areas if possible.

The project is expected to take several weeks and may be affected by inclement weather or equipment problems.

Thank you for your patience.

North Cornwall Township Highway Department

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS